Project Timeline Management - GanttWhat is a Gantt chart? Every time we, in our project management careers, go through the rigmarole of our projects, trying to meet and beat our own-set goals, a silent word of gratitude goes to the heavens for Henry Gannt for conceiving this intuitive diagram for charting project timelines, for the Gannt Diagram allows us to excel in this chosen career.
HistoryHenry Gantt (1861-1919), a mechanical engineer, management consultant, and industrial advisor developed Gantt charts in the 1910's. Not as commonplace as they are today, Ghant charts were innovative and new during the 1920's, where Gannt charts were used on large construction projects like the Hoover Dam started in 1931 and the Eisenhower National Defense Interstate Highway System started in 1956. Now, a staple project management tool and buzzword in the repertoire of modern project management tools today, Gannt charts are routinely deployed in the by project managers, planners, and system developers. Working on projects without them is unthinkable, except in the rare case when the inherently nature of the work does not require them. The Gantt chart has attained world renown, known in Spanish as carta Gantt (Gannt Chart), grafica / graficas de Gantt (Ghant Graphic), and diagrama / diagramas de Gantt (Gannt Diagram) and in French as diagramme de Gantt (Gaant Diagram), indeed the whole world speaks this common language of project representation. Henry L. Gantt's global contribution to the modern project management is honored today through the The Henry Laurence Gantt Medal. This medal, established in 1929, is awarded for distinguished achievement in management and service to the community. Practical Application
Once the Gantt charts are drawn up, and project execution begins, we start comparing our actual, ground-level performance against what was planned. This comparison is possible by checking the field reports against the Gantt charts. Thus, we get to benefit from them in two immediate ways:
Additional Resources
How to make a Gantt chart Now, for each task in a row, we draw a horizontal (preferably hollow) bar alongside, with its start point in the column representing the date when it is scheduled to begin, and the end point in the column of the date when it is expected to end. Once these horizontal bars are drawn, we step back and get to observe the tasks that are going to run sequentially, in parallel, or overlap. After the project has commenced, managers simply fill in the hollow bars to a length that is in proportion to the fraction of the work that has been completed, for every task. In order to judge where we stand on any given date - say today, we can draw an imaginary vertical line through the chart at the current date - this is a "snapshot line". The tasks that are supposed to have completed fully shall be to the left of this snapshot line. If they are indeed completed, their hollow bars shall have been completely filled. Partial filling indicates slip-ups. Tasks that are crossing the snapshot line are current tasks in hand; well, at the least they are tasks that were scheduled to have begun before today. If the horizontal bar on such tasks is filled in to the left of the line, then the current tasks are behind schedule; if they are filled in to the right of the line, then they are ahead of schedule. Future tasks, of course, will lie completely on the right of the snapshot line. Complex projectsWhat has been described above is for simple projects. Ideally, tasks in simple projects would not go beyond a single page, which makes them manageable. Often, and especially in complex projects, each task may be broken into smaller and more easily manageable subtasks. These subtasks may be moved to subordinate charts, with their own timelines. In management terminology, the process - of breaking up of these tasks into independent unit-tasks that can be completed on their own - has been given an exotic name of WBS, or "Work Breakdown Structure". This process enables the manager's mind to grasp the project in its entirety as well as to think in terms of allocating resources, assign responsibilities, and measure and control the project, for every task and sub-task. Further, in team-oriented projects, where each task is to be handled by different personnel, there might be an additional column against each task, where initials of these personnel may be entered, to identify who is supposed to be doing what. Project MilestonesAchieving milestones are occasions for celebration, to pop the champagne. They help to boost the morale of personnel involved in making the project a success. If the Gantt chart is drawn up along with suitable (and achievable!) milestones, by using some special symbol such as brightly-colored diamonds, and the chart is kept in some centrally visible place, it would motivate all the people to achieve them. These milestones could range from perhaps the approval of p roject design by the customer, or completion of project prototype, to delivery of individual modules by different teams. ConclusionAfter Henry Gantt showed the way, quite a wealth of management literature has evolved on how to manage projects. Indeed, Project Management is a full-fledged discipline in itself, deserving of a separate academic degree for those who pursue it as a career and profession. More powerful models have evolved in the past few decades, which strive to capture the complexity of human endeavor and track and monitor its progress. The Gantt chart continues to be used in some avatar or the other in all such models. And for simple projects, Gantt chart is the solution. Addendum: Gantt SpellingWidely discussed, but difficult to spell, and far more than a buzzword, Gantt's unusual surname gives rise to much dismay as people search for information on Gannt Charts, Ghant Charts, and Gannt Charts. As such, I have included these common misspellings so that when your boss tells you to create a Gannt Chart, Ghant Chart, or Gannt Chart - this resource will be readily located, and your life as a project manager can soar to new heights. |
|
|||||||||
|
© Copyright 1998-2005 Envision Software, Incorporated Tampa, Florida This work is licensed under a Creative Commons License . Questions? Comments? Send them to the Webmaster |
||||||||||